• Skip to main content
  • Skip to primary sidebar
  • Skip to footer
Saturday, November 07, 2026 - 69°
  • Health
  • Calendar
  • Cops Corner
  • Real Estate
  • Contests
  • E-Editions
  • Legal Notices

Plant City Observer

Plant City News and Real Estate

  • News
    • Business
    • Your Town
  • Neighbors
    • Around Town
    • ClubHubbub
    • Creative Space
    • Faith
    • Obituaries
    • Relay for Life
    • Florida Strawberry Festival
    • Schools
  • Opinion
  • Sports
    • High Schools
    • Athlete of the Week
    • Youth Sports
    • Gridiron Report
  • Photos
  • Videos
News April 10, 2025 7:00 am

GRANT STREET STILL BLOCKED

By Dave Hoover

ISSUES AT THE SITE GREATLY ADDED TO COMPLEXITY.

Share This Post
  • Facebook
  • Pinterest
  • Twitter
  • Linkedin

A lift station has a pump that lifts wastewater to a higher point so it can again flow by gravity to a treatment plant. In Plant City, these pumps and pipes are in a wet well. The wet well is where the wastewater is contained. Generators and electrical components sit on a concrete pad, above and around the lift station. Cellular antennas are attached to the above-ground components to transmit data to The City of Plant City’s Water Reclamation Facility control room so staff can monitor the system. Slatted, chain-link, privacy fence surrounds each lift station. There are more than 50 lift stations placed in strategic spots around the city.

In 2022, the city commission approved a project to construct a new lift station south of West Grant St, adjacent to Dr. Hal & Lynn Brewer Park. The plan was for the new station to replace the old lift station No. 7—which was built in the early 1960s. The replacement was intended to manage the current wastewater flows at the site and from the new Parkside Townhome Development. The project also involved extending the city’s sewer system to the new pump station and decommissioning the old Lift Station No. 7. 

Grant Street was closed in May 2024 as a step to completing the project. However, during construction, workers discovered the soil at the planned location is muck. Geotechnical data confirmed that installing the sewer main there would end up with it sinking—therefore requiring the expense of doing the project again and again. Because of this, the project engineers had to change the plans for construction and installation of the new lift station No. 7—causing plans to have to be reconfigured, and causing delays. 

Adding insult to injury, in June 2024, in the midst of the work on the new lift station, a sinkhole was discovered on the site. This required the plan to be revised again because the sinkhole had to be stabilized before the new lift station could be completed. With projects like this, engineers are largely flying blind because it is difficult to determine the volume of empty space that makes up a sinkhole. To stabilize a sinkhole, grout is injected into the hole, and the ground around it, until it is firm. Stabilizing this sinkhole took six injection points to a depth of 95 feet, 493 feet of grout castings, and 310 cubic yards of grout. Solving this problem caused more delays, and added an extra $96,553 to the project cost.

Now that the sinkhole has been stabilized, the work is in its next phase—dewatering the site down to a depth of 30 feet. “We are dealing with a combination of a wetland area there—basically a swamp—that was under the roadway, and, immediately adjacent to it, a sinkhole,” City Manager Bill McDaniel said. “Between the two it has created a very complex situation. The project was derailed and delayed by the combination of the wetland area and the existing sinkhole. So, we have had to stabilize the sinkhole. Then we have to dewater to put in the lift station, because lift stations go underground. A lift station has its own capacity to keep itself from flooding with the various pumps that are installed, as well as to provide the pressure to move the effluent along through the pipes in the sewer system. Lift stations are not a luxury. They are not an option if you want your toilets to work.” 

Currently, the city has the revised lift station project design completed, and they have the contractor on board. “Sinkholes tend to have water in them, and when you are dealing with a swampy area—that has water,” McDaniel said. “So, we are dealing with quite a bit of saturation there. We have high capacity pumps on it, and they run, if not 24/7, most of the day. Currently, that water pumps off to the Brewer Park pond, and then drains out through the West Side Canal.”

The anticipated date Grant Street will be reopened is December, 2025.

Related Stories

Filed Under: News

Primary Sidebar

Newsletter Sign Up

Sign Up To Receive Our News In Your Inbox!

Stay Connected

  • Contact Us
  • Privacy Policy

Footer

Contact Us

110 E. Reynolds Street Suite 100B Plant City, FL 33563 View Map

813-704-6850

info@plantcityobserver.com

Other Publications

Browse a digital collection of our other publications, magazines and special sections such as Season Magazine, Health Matters, Holiday Gift Guide and more.

View All E-Editions

Newsletter Sign Up

Sign Up To Receive Our News In Your Inbox!

Copyright © 2026 Plant City Observer, All Rights Reserved

Site created by Graphite Media.us and Red Key Designs/Red Key.io
  • Home
  • News
    ▼
    • Business
    • Your Town
  • Neighbors
    ▼
    • Around Town
    • ClubHubbub
    • Creative Space
    • Faith
    • Obituaries
    • Relay for Life
    • Florida Strawberry Festival
    • Schools
  • Opinion
  • Sports
    ▼
    • High Schools
    • Athlete of the Week
    • Youth Sports
    • Gridiron Report
  • Photos
  • Videos
  • Health
  • Calendar
  • Cops Corner
  • Real Estate
  • Contests
  • E-Editions
  • Legal Notices